AEP Texas representatives plan to upgrade the local electric transmission system in Cameron County. The Brownsville 138kV Transmission Line Rebuilds Project involves rebuilding approximately 44.5 miles of 138-kilovolt (kV) electric transmission line to enhance electric reliability for area residents and businesses.
November 4 and 5, 2026: AEP Texas representatives plan to host public open houses where attendees can learn about the project, view detailed maps and talk with project team members. There will be no formal presentation, so guests may arrive at any time. Information presented at each open house will be the same.
*Move slider to view project timeline
AEP Texas crews plan to install single-pole steel structures.
Typical Structure Height: Approximately 85 - 100 feet*
Typical Distance Between Structures: Approximately 400 - 600 feet*
Typical Right-of-Way Width: Approximately 100 feet*
*Exact structure types, height and right-of-way requirements may vary
AEP Texas serves more than 900,000 electric consumers in the deregulated Texas marketplace.