Roselms - Kalida Area Improvements Project


The Roselms-Kalida Area Improvements Project involves rebuilding about 30 miles of power line and building about 10 miles of power line.

Company representatives plan to update, supplement and acquire new easements where necessary. Improvements reduce the likelihood of power outages and speed recovery of service when outages occur.

Project Updates

Summer 2026: Company representatives are currently revising the project schedule and plan to provide an update to community soon.

AEO Ohio representatives announces the project in summer 2020. In 2024, the proejct was placed on hold while the team re-evaluated the project schedule. Since then, the project team has reviewed and revised the schedule. The timeline below incorporates those updates.

Landowners along the line route can expect to hear from a Contract Land Services (CLS) agent, AEP Ohio's right-of-way representative for this project, to answer questions about the project, including easements, field activities and next steps.

To view the previously recorded Town Hall event on March 18, 2021, please click on the link below

Roselms-Kalida Live Virtual Town Hall

Map

Project Map (PDF)

Timeline

Open project timeline modal

Structures

Open project structure modal

The project involves the use of single, steel poles.

Structure Height: Approximately 80 feet
Right-of-Way Width: Approximately 60 feet

*Exact structure types, height and right-of-way requirements may vary

Resources

Property Easements Project Fact Sheet Access Roads Field Activities

AEP Ohio provides electricity to nearly 1.5 million customers.

www.AEPOhio.com

AEP Ohio Outreach

614-933-2998
AEPOhio_Outreach@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.