Ashdown - 12th StreetTransmission Line Rebuild Project


Southwestern Electric Power Company (SWEPCO) representatives plan to improve the electric transmission system in the Texarkana area. Crews plan to begin construction in early 2024 and conclude in late 2024.

The Ashdown - 12th Street Transmission Line Rebuild Project involves upgrading about 19 miles of transmission line in Miller and Little River counties to enhance reliability, strengthen infrastructure against severe weather and support the area's future growth. This project requires SWEPCO representatives to file a Certificate of Environmental Compatibility and Public Need (CECPN) with the Arkansas Public Service Commission (APSC).

Project Updates

Fall 2024: SWEPCO crews and contractors continue to work on rebuilding this line between Texarkana, Ark., and Ashdown, Ark. SWEPCO representatives expect crews to reach the Ashdown area in October to finish the last leg of the rebuild project. Crews plan to conclude construction in late 2024.

Late 2023: Crews plan to start pre-construction activities in early December to prepare the right-of-way for construction. This work may include:

  • Placing stakes and ribbon within the company’s easement on your property
  • Installing temporary gates, fencing and access roads
  • Installing culverts for water management

In early 2024, SWEPCO contract crews plan to trim or remove trees and other woody-stemmed vegetation, as appropriate, within the transmission line right-of-way, which extends 50 feet from the center of the power line on each side. Crews also plan to identify trees that are dead or dying just outside the right-of-way, and crews will contact landowners about necessary steps if trees are deemed hazardous to the line. This maintenance helps ensure the safe operation and reliability of the power line. Please visit aeptransmission.com/property/forestry.php to learn more about SWEPCO’s transmission line vegetation management program.

SWEPCO representatives expect transmission line construction to begin in spring 2024 and conclude in late 2024.

Spring 2023: SWEPCO representatives plan to conduct boundary survey activities along the line, starting in late May and concluding in late June. Some of the survey work may require crews to place stakes and ribbon on your property.

As the project has developed, SWEPCO representatives have shifted the construction schedule. SWEPCO representatives expect to start pre-construction activities in late 2023, with transmission line construction following shortly thereafter in early 2024. Crews plan to finish construction activities in late 2024.

Early 2023: On Jan. 17, 2023, SWEPCO representatives filed an application for a Certificate of Environmental Compatibility and Public Need (CECPN) with the Arkansas Public Service Commission (APSC). Landowners are invited to monitor the proceedings here and participate as they see fit, but all interventions or limited applications must be filed within 30 days of the CECPN filing, unless good cause is shown pursuant to Arkansas Code Ann. §23-18-517. Volkert, Inc., serves as SWEPCO's right-of-way representative for this project. Volkert agents plan to contact affected landowners to discuss field activities, easement acquisition and construction.

Late Fall 2022: SWEPCO representatives hosted an in-person open house in Texarkana at North Heights Community School on Nov. 15 for affected members of the public to learn more about the project from project team members. Volkert, Inc., serves as SWEPCO's right-of-way representative for this project. Volkert agents plan to contact affected landowners to discuss field activities, easement acquisition and construction. As of November 2022, SWEPCO representatives expect transmission line construction to start in fall 2023 and finish in late 2024.

 

 

Timeline

 
Open project timeline modal
 

Structures

Open project structure modal

SWEPCO engineers plan to use single-pole steel structures.

Typical Structure Height: Approximately 90 feet*
Typical Distance between Structures: Approximately 600 feet*

*Exact structure design, height and right-of-way requirements may vary.

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Southwestern Electric Power Company (SWEPCO) serves 535,000 customers in western Arkansas, northwest and central Louisiana, northeast Texas and the Texas Panhandle.

SWEPCO.com

Matthew Hames

Project Outreach Specialist
918-237-6736
mchames@aep.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.