Coleman - Grapevine Transmission Improvements Project


Kentucky Power and Appalachian Power representatives plan to increase electric reliability by making transmission line upgrades in Pike County, Kentucky and Mingo County, West Virginia.

Crews plan to begin construction in fall 2027 and conclude by spring 2029.

Project Updates

September 1, 2026: Following a project announcement and open house in August 2026, company representatives continue to evaluate options for a proposed line route. We are committed to keeping you informed throughout this process and plan to provide updates as soon as they're available.

July 30, 2026: Appalachian Power and Kentucky Power invites community members and landowners in the project area to an in-person open house to speak with project members to learn more. There is no formal presentation, so landowners can attend at any time at a location most convenient to them.

Tuesday, August 18, 2026, from 5 - 7 p.m. - Old School Events - 24 Runyons Branch, Pinsonfork, KY 41555

Landowners are encouraged to submit their feedback about the project by Tuesday, September 1. To provide comments on how this project affects your property or special conditions related to your property, you may use the comment form below or call 833-236-7696.

Timeline

*Move slider to view project timeline

Structures

Open project structure modal

The project primarily involves the use of steel H-Frames and some monopole structures.

Existing Average Structure Height: Approximately 50 feet*
Proposed Structure Height: Approximately 90 feet*
Proposed Right-of-Way Width: 100 feet*

*Exact structure types, height and right-of-way requirements may vary

Substation

Open project Substation modal

Substations serve as electrical intersections directing the flow of electricity and either decrease or increase voltage levels for transport. Substations transform 69-kV and 138-kV electricity into lower distribution level voltages such as 34.5-kV, 12-kV, or 7.2-kV.

*Substation shown is a general depiction of the proposed facilities for the project. It does not represent final design.

Resources

Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Appalachian Power serves approximately 1 million customers in West Virginia, Virginia and Tennessee.

www.AppalachianPower.com

Micaela Harris

Project Outreach Specialist
833-236-7697
APCO_Outreach@aeptransmission.com

Submit a Message

*Required field. By clicking submit, you agree to AEP's Privacy Policy.

Please complete the ReCAPTCHA to submit the form. If you have difficulty, use the audio challenge option.

Paper plane

Your message has been sent! We'll be in touch shortly.