Riverside - South HudsonTransmission Improvements Project
Public Service Company of Oklahoma (PSO representatives plan to rebuild a 138-kilovolt (kV) transmission line in the south Tulsa and Jenks area to increase electric reliability and strengthen the local power grid to accommodate future load demands. Crews plan to start construction in early 2026 and conclude in spring 2027.
The project involves:
- Rebuilding about 10 miles of 138-kilovolt (kV) transmission line between the South Hudson Substation in Tulsa and the Riverside Substation in Jenks. This includes rebuilding about 7.5 miles of the 138-kV Riverside - South Hudson transmission line and about 2.5 miles of lines connecting other south Tulsa substations to the Riverside - South Hudson transmission line.
- Upgrading substation equipment
- Trimming or removing trees and woody-stemmed vegetation that have grown within PSO's right-of-way
Project Updates
Spring 2025:
TREE TRIMMING IN YOUR AREA
Unrelated to this transmission line rebuild project, PSO forestry representatives want property owners to know contractor tree crews are conducting vegetation management activities such as tree trimming and cutting within or near transmission line rights-of-way (ROW) crossing properties in parts of this same project area.
You may see trimming crews working along the transmission line path through parts of south Tulsa and Jenks, including:
Tulsa
- Residential areas along South Hudson Avenue between 51st and 61st streets
- Residential areas between 61st and 81st streets, and between South Sheridan Road and South Lewis Avenue
- Portions of the Oral Roberts University and Victory Church campuses
- Areas along Riverside Drive between 81st and 91st streets
Jenks
- Residential areas near the Riverwalk
- Areas by the Oklahoma Aquarium and south to PSO's Riverside Power Station
Crews plan to conclude this work in July.
Forty percent of power outages are due to overgrown trees and other vegetation. Regular vegetation management practices such as trimming and clearing trees near or within the ROW helps balance the need for reliable electric service with respect for the natural environment and the community. If you have questions about this work, please contact us at 800-272-4826 or PSO_Outreach@aep.com.
Spring 2024: As this project has evolved, the project timeline has shifted. Previously crews planned to start construction late this year and conclude in early 2025. Now, PSO representatives plan pre-construction activities such as right-of-way access preparation and tree trimming/clearing to begin in late 2025, followed by transmission line construction in early 2026. Company representatives expect construction to conclude in spring 2027.
O.R. Colan Associates (ORC) serves as PSO's right-of-way representative for this project. ORC right-of-way agents plan to contact affected landowners to discuss field activities, easement acquisition and construction.
Fall 2023: PSO representatives hosted an in-person open house in Tulsa at Key Elementary School on October 12 for affected members of the public to learn more about the project from project team members. PSO representatives continue to talk with affected landowners along the power line route to discuss necessary field activities, the construction process and PSO's plans for trimming or removing trees that have grown within the company's right-of-way.
Summer 2023: As this project has evolved, the timeline has shifted. Crews planned construction to begin this fall and conclude in late 2024. Now, PSO representatives expect pre-construction activities such as right-of-way access preparation to begin in late 2024, followed by transmission line construction in early 2025. Company representatives expect construction to conclude in late spring 2026.
Timeline
Structures
Crews plan to install steel single poles on this project.
Current:
Typical Structure Height: Approximately 60-70
feet*
Structure Material: Wood
Planned:
Typical Structure Height: Approximately 95 feet*
Typical
Right-of-Way Width: 50-100 feet*
Typical Distance Between Structures: Approximately 300
feet*
Structure Material: Steel
*Exact structure design, height and right-of-way requirements may vary.
Resources
Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities Forestry PracticesPublic Service Company of Oklahoma serves 538,000 customers in Oklahoma.
Matthew Hames
Project Outreach Specialist
918-237-6736
mchames@aep.com
Your message has been sent! We'll be in touch shortly.