Sabine ParishTransmission Improvements Project
SWEPCO officials plan to enhance the local power grid in northwest Louisiana. These enhancements support economic development in the area and ensure continued reliable service for area customers.
Project Updates
Spring 2025: As this project has evolved, the timeline has shifted. SWEPCO representatives expect construction to begin in fall 2025 and conclude in fall 2026. O.R. Colan Associates (ORC) serve as SWEPCO’s right-of-way representative for this project. ORC right-of-way agents continue to contact affected landowners to discuss field activities, easement acquisition and construction.
Timeline
Structures

SWEPCO crews plan to install single-pole steel structures.
Typical Height: 75 feet
Typical Distance Between Structures: 400 feet
Typical Right-of-Way Width: 80 feet*
Proposed Substation Footprint: 220 by 200 feet
*Exact structure types, height and right-of-way requirements may vary
Typical Substation

Proposed Substation Footprint: 220 by 200 feet
Resources
Property Easements Virtual Open House Project Fact Sheet Project Map Access Roads Field ActivitiesSWEPCO serves 535,000 customers in western Arkansas, northwest and central Louisiana, northeast Texas and the Texas Panhandle.
Michael Harris
Project Outreach Specialist
918-231-8047