translate-globe-icon

Catoosa - VerdigrisTransmission Line Rebuild Project


Public Service Company of Oklahoma (PSO) representatives plan to strengthen the electric system in southwestern Rogers County by rebuilding an aging transmission line. PSO representatives expect to begin construction in fall 2025 and conclude in spring 2026.

The project involves:

  • Rebuilding about 11 miles of the 138-kilovolt Catoosa - Northeastern Power Station transmission line between PSO's Catoosa Substation in Catoosa and KAMO Power's Verdigris Substation in Verdigris
  • Rebuilding about 3 miles of lines connecting other substations to the Catoosa - Northeastern Power Station transmission line
  • Upgrading substation equipment along the power line route

Pre-construction activities may include:

  • Trimming or removing woody-stemmed vegetation, and removing or relocating non-habitable structures from PSO's right-of-way
  • Installing temporary gates, fencing and access roads
  • Installing culverts for water management

PROJECT UPDATES

Spring 2024: PSO representatives hosted an in-person open house in Verdigris at the Verdigris Upper Elementary School Cafeteria on February 13 for affected members of the public to learn more about the project from project team members.

Contract Land Staff (CLS) serves as PSO’s right-of-way representative for this project. CLS right-of-way agents are contacting affected landowners to discuss field activities, easement acquisition and construction.

Early 2024: PSO representatives will host an in-person open house on Tuesday, Feb. 13, 2024, at the Verdigris Upper Elementary School Cafeteria at 8204 E. 540 Road, Claremore, OK, 74019. The event will be from 5-7 p.m. and landowners affected by the project are invited to attend the open house to learn more about the project, the construction process and PSO's vegetation management program. There is no formal presentation, so attendees can arrive at any time during the event.

Contract Land Staff (CLS) serves as PSO’s right-of-way representative for this project. CLS right-of-way agents plan to contact affected landowners to discuss field activities, easement acquisition and construction.

Timeline

 
Project Timeline
 

Structures

Structure

PSO representatives plan to use steel single pole structures on this project.

Typical Structure Height: Approximately 90 feet*
Typical Right-of-Way Width: 100 feet*

*Exact structure design, height, and right-of-way requirements may vary

Resources

Virtual Open House Project Fact Sheet Project Map Access Roads Field Activities

Public Service Company of Oklahoma serves 538,000 customers in Oklahoma.

www.PSOklahoma.com

Matthew Hames

Project Outreach Specialist
918-237-6736
mchames@aep.com

* Required field. By clicking submit, you agree to AEP's Privacy Policy.

Paper plane

Your message has been sent! We'll be in touch shortly.