LEGEND

    Sardinia Area Improvements

    AEP Ohio is improving the electric transmission system in Brown County. The Sardinia Area Improvements involves building about 5 miles of new 138-kilovolt (kV) transmission line, upgrading a substation and retiring about 12 miles of 69 kV transmission line. 

    Adding the new transmission line and upgrading the substation provides an additional power source to the electric transmission grid and updates aging infrastructure to provide reliable electricity to area customers.

    The line will likely run through Eagle Township in Brown County, east of Sardinia. AEP Ohio anticipates building the new transmission line primarily with steel single pole structures that will be approximately 110-feet tall.

    The projected costs of the upgrades are approximately $19 million.

    Project Updates

    February 2019: The OPSB granted a Certificate of Environmental Compatibility and Public Need to construct this project in February. The transmission right-of-way group is currently working to acquire the necessary land and easements for construction.

    Spring 2018:  AEP Ohio Transco filed an application with the Ohio Power Siting Board requesting permission to construct this project. 

    A local public hearing for the proposed Sardinia Area Improvements will be held on Thursday, October 11, 2018, at 6 p.m., at the Brown County Public Library - Sardinia Branch, Community Room, located at 13309 Purdy Road, Sardinia, Ohio 45171. At this local public hearing, the public will be given an opportunity to comment on this project to the Ohio Power Siting Board (OPSB). AEP Ohio and its affiliate, AEP Ohio Transmission Company Inc., invite all residents and property owners who wish to present written or oral testimony to attend this public hearing. The OPSB will consider comments from the public and the OPSB Staff Report when evaluating the application.

    An evidentiary hearing will be held on Monday, November 5, 2018, at 10 a.m. in Hearing Room 11-C at the offices of the Public Utilities Commission of Ohio, 180 East Broad Street, Columbus, Ohio 43215. This hearing is open to the public; however, participation is limited to the parties in the case.

    Project Releases

    Fact Sheet

    Timeline


    Structures

    The project will use steel single pole structures that will be about 110-feet tall. The structures will be located in an approximate 100-foot wide right-of-way corridor.

    *Exact structure, height and right-of-way may vary


    * The accompanying map depicts the project area. It should be noted that the map contained on this site is for information purposes only. AEP reserves the right to alter, change, or amend the map at any time without notice and AEP provides no warranty about the accuracy of content. Keep this in mind when reviewing this map. However, AEP will make all attempts to keep this map as accurate as possible. If you have any questions about the accuracy of the current map please Contact Us.