AEP Ohio representatives plan power grid upgrades to improve electric reliability for customers in south Columbus and provide power to a future customer.
The Parsons Avenue Transmission Project involves:
The planned improvements provide a new power source to strengthen the local electric power grid, provide power to a future customer in the area and support economic development.
Company officials expect construction to begin in fall 2021 and conclude in summer 2023.
April 2021:
October 2021:
AEP Ohio representatives have filed a Letter of Notification for 2.3 miles of 138-kV transmission line connecting the new Cyprus Substation to an existing transmission line with the Ohio Power Siting Board as the Cyprus 138 kV Extension Project, Case No. 21-1056-EL-BLN. The Letter of Notification to construct, operate and maintain this facility awaits OPSB review.
AEP Ohio representatives have filed a Letter of Notification for 2.3 miles of 138-kV transmission line connecting the new Cyprus Substation to an existing transmission line with the Ohio Power Siting Board as the Cyprus 138 kV Extension Project, Case No. 21-1056-EL-BLN. The Letter of Notification to construct, operate and maintain this facility awaits OPSB review. AEP Ohio representatives have filed a Construction Notice for .6 miles of 138-kV transmission line connecting the proposed Cyprus Substation to the customer's substation with the Ohio Power Siting Board as Hartman Farms 138 kV Extension No. 5 and No. 6 Project, Case No. 21-1057-EL-BNR. The Construction Notice to construct, operate and maintain this facility awaits OPSB review.
July 2021:
AEP Ohio representatives have filed a Letter of Notification with the Ohio Power Siting Board for the proposed Cyprus Substation. The Letter of Notification to construct, operate and maintain this facility awaits OPSB review.
Cyprus – Parsons 138 kV Transmission Line Project Letter of Notification - April 7, 2022
Cyprus – Parsons 138 kV Transmission Line Project Public Notice - April 7, 2022
Beatty-Canal Street 138 kV Cut-In Project Construction Notice - February 11, 2022
Cyprus 138 kV Extension Project Letter of Notification - October 28, 2021
Cyprus 138 kV Extension Project Public Notice - October, 2021
Hartman Farms 138 kV Extension No. 5 and No. 6 Project Construction Notice - October 28, 2021
Cyprus 138 kV Station Project Letter of Notification - August 3, 2021
Cyprus 138 kV Station Project Public Notice
The project involves installing steel poles.
Typical Pole Height: Approximately 100 feet*
Right-of-Way Width: Approximately 80-100 feet*
* Exact structure, height and right-of-way may vary
AEP Ohio provides electricity to nearly 1.5 million customers.
Project Outreach Specialist
380-205-5381
brecker@aep.com
Your message has been sent! We'll be in touch shortly.